We have had someone create a new project number in the field and log data under this project. I understand this is not correct practice, but is there a way we can transfer this data over to the correct project that is linked to ESdat? Furthermore, as the project number created in the field was not setup in ESdat we cannot access/see any of the samples that were collected under this project number.

Warwick Wood  
#2 Posted : Sunday, July 09, 2017 1:29:17 PM(UTC)
Warwick Wood
Rank: Administration

Reputation:

Groups: Registered, Administrators
Posts: 422
Man
Location: Byron Bay

Was thanked: 9 time(s) in 9 post(s)

If, in PLog Cloud, you select the two Projects using the checkboxes, you can then Merge the selected Projects using the Action dropdown.

You may need to set the "last synch" date in ESdat to back before this data was collected so that this data from the other project is collected from PLog.

Regards,

Warwick

You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.